The volcanic mass of Lilleshall Hill, with its prominent monument to the
Dukes of Sutherland, stands out of the East Shropshire Plain. It is
Pre-Cambrian in origin and, with the Wrekin, amongst the oldest rocks in
It is not known when men first began to cut the limestone as a building
material but the adjacent Lilleshall Abbey was certainly built from it in the
12th century. Following the dissolution of the Monasteries in the 1530s, the
estate was bought from the Government by the Leveson family who had made their
fortune in the
Although the earliest reference to limestone working in Lilleshall was
in 1625, it wasn't until the 18th century that industry generally began to
predominate. Sir John Leveson became Earl Gower in 1746 and the industrial
story really began when his son Granville Leveson Gower became the second Earl
in 1754. He was a typical high born gentleman of his age - landowner, Member of
Parliament, Lord of the Admiralty, Lord Privy Seal and Lord Chamberlain to King
George III. Despite all these duties, he took an active interest in the
efficient running of the local estates, namely Sherrifhales, Lilleshall,
Donnington Wood, St Georges, Priorslee, Wombridge and Snedshill.
His brother-in-law was Francis 3rd Duke of
The new partnership soon recognised that a better communication system
was required between the widely dispersed sites and in 1765 began the
construction of a canal. It ran from
This expansion entailed the removal of a large quantity of overburden to
get at the limestone. To get rid of this, a length of canal was dug to a nearby
kettle hole and the spoil taken here in tub boats to fill in marshy ground and
make it suitable for agriculture. The quarry workings were linked to the main
canal near Hugh's Bridge by a branch canal which was unfortunately 18 metres
lower. To overcome this, the branch canal went under the main canal in a tunnel
with a shaft to link the two. Boats would be moored underneath the shaft and a
crane lifted pallets of stone up to other boats in the canal above.
Although some quarries could work the two shallowest limestone beds by
opencast methods, to reach the lower beds it became necessary to mine the
limestone since the cost of removing the overlying strata was too great. This
also applied where shallower beds dipped downwards and the overburden increased
proportionately. The mines were worked on the pillar and stall system which
left 25% of the limestone behind as pillars to support the roof. Tunnels were
driven down dip about 9 metres wide and, after a distance of about 18 metres,
the tunnels were linked by a cross passage also 9 metres wide. The process
would then be repeated, leaving a series of pillars about 9 metres square. For
shallow beds, the mine passages would continue in from the existing quarry face
but, for lower beds, a shaft would be sunk to the appropriate level and the
same mining system employed.
Some of the limestone was converted to quicklime on site by burning it
in kilns. These consisted of 7.5 metre deep shafts with a grate at the bottom
connected to the outside by a horizontal service tunnel. They were fuelled by
coal carried on the canal from the nearby
Donnington collieries. The limestone and fuel were stacked at the shaft
bottom, the fuel set afire and the whole thing left to burn for several days. A
draught was sucked in along the tunnel and up the chimney shaft to increase the
fire temperature. After the fire had died down, the lime could be broken up
into small lumps for transport. Transport of limestone and coal to the kilns
themselves was originally by horse and cart but these were later replaced by
lines of "L" shaped cast iron rails. Since the quicklime becomes
caustic when wet, it was not advisable to transport it by rail. As a result, it
was usually stored by the kilns and picked up by customers themselves.
Although some of the limestone was converted to slaked lime for cement
and local land improvement schemes, the majority was sent to be used as a flux
in the iron furnaces. It was transported on the canal in long lines of tub
boats (see Figures 50-51) which were 6 metres long, 1.9 metres wide and 1.2
metres deep. Due to the intricate network of canals in the area, this meant
that it could usually be transported directly from the quarry to the iron works
without being transhipped.
The quarries at Colliers Side originally worked the shallower beds
opencast but the workings were eventually continued underground with inclines
linking them to the tramways above. The extracted waste material was used to
build great embankments across the quarry in which kilns were built, as well as
two tunnels for access. Tramways ran along the top of the embankment to feed
the kilns and to carry material to the canal. Shafts from 45-75 metres deep
were also sunk to work the lower beds and an open trench west of
The Lilleshall Partnership was creating a profitable business from the
Colliers Side quarries and this was not unnoticed by the neighbouring Leeke
family. Their land was in the parish of Church Aston but they were landowners
rather than industrialists. Their main venture was at Blackberry Bank Mine,
which had originally been worked from the 17th century, and they sunk shafts
over 36 metres deep. Pumping engines, probably of the Newcomen type, were
erected but they were less successful than they expected. This led them to
leasing the exploration rights to the Partnership who had linked Blackberry
Bank Mine to their canal system by 1798. By this time, however, the mine was
almost worked out and several 120 metre deep shafts had been sunk to the east
at what was to become the Pitchcroft Mine.
By 1800, the mining industry of the area was at its fullest extent but
the Partnership was almost finished. Both the Gilberts were dead and Earl Gower
was 79. The younger son, Lord Granville Leveson-Gower, acquired all the shares
in the Partnership and formed the Lilleshall Company in 1802 with John Bishton,
James Birch, John Onions and William Phillips. The Blackberry Bank Mine was
abandoned and other quarries and mines around Lilleshall were finished by the
1830s. Although twin exploratory shafts 213 metres deep were sunk at Crow
Hayes, work now concentrated on the Pitchcroft Mine.
This mine worked in a restricted area but may have produced over a
million tons of limestone during its life. In 1846, the Stafford-Wellington
railway was built and this passed right by the main shaft of the mine. A short
branch was built to the mine and this made it much easier to transport
limestone to the Donnington furnaces. The mine was notorious for accidents and
a typical one occurred in 1858 in which three men were killed when "an
immense layer of stone" fell on them.
In 1860 a real disaster struck when water was found to be rising through
the floor in old workings. This rapidly became a flood and the workings had to
be abandoned when the pumps could not keep pace with the inrush (see Figure
54). No human lives were lost but the pit ponies could not be rescued and they
were left to their fate, the rotting carcases polluting local water supplies
for some time afterwards. It was estimated that over 300 gallons of water per
minute were entering the mine and portable pumps capable of removing 400
gallons per minute were brought in. Within days, however, the inflow had
doubled and the mine was lost. It is believed that exploratory workings had
passed through the Brocton Fault and found workable stone at a different
horizon, this then being left until required. Beyond the fault, however, was
the
This was originally called Sour Leasow Pit and had begun as twin
exploratory shafts 60 metres deep, rapidly expanding to meet the local needs
for limestone. The mine was finally abandoned in 1883 but produced about
188,000 tons of limestone during 21 years of working. It averaged 7,500 tons
per year which was taken to a small basin on the nearby canal and carried in
tub boats to the furnaces. Its demise was due to the fact that the Company
could bring in limestone cheaper from Wenlock Edge and Nantmawr near Oswestry,
despite the extra distance involved.
Thus ended the industrial history of Lilleshall and the surrounding
area. All mine buildings and equipment were removed and the dumps planted with
trees. The workings flooded and the shafts were capped with brick
"beehives" (see Figure 98). The tramways were removed and the canal
system became derelict, part of the main course being filled in during the
construction of the Lilleshall Hall drive in 1896.